Dept. of Trans. PROGRESS Serial No. Contract No. 22-140-19-15 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 73% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 043 Payment period ending: 05-20-22 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 16470 W BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 183,771,331.79 3,761,788.77 2. a. Extra Work 13,306,679.28 134,680.90 b. Adustment Comp. 90,106.60 0.00 3. Materials on Hand 663,966.19 374,398.00 4. Earned Subject to Retention 197,832,083.86 4,270,867.67 5. Mobilization 22,400,000.00 0.00 6. Total Work Completed 219,568,117.67 7. Deductions -29,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 220,203,083.86 4,260,867.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,260,867.67