Dept. of Trans. PROGRESS Serial No. Contract No. 23-022-10-09 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 73% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 051 Payment period ending: 01-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 191,353,042.82 -622,338.05 2. a. Extra Work 16,059,486.80 2,091,666.47 b. Adustment Comp. 4,079,493.85 -615,600.80 3. Materials on Hand 416,905.48 -374,398.00 4. Earned Subject to Retention 211,908,928.95 479,329.62 5. Mobilization 22,400,000.00 0.00 6. Total Work Completed 233,892,023.47 7. Deductions -27,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 234,281,928.95 479,329.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 479,329.62