Dept. of Trans. PROGRESS Serial No. Contract No. 23-111-19-05 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 73% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 054 Payment period ending: 04-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 192,134,716.77 197,950.27 2. a. Extra Work 16,743,906.85 21,512.74 b. Adustment Comp. 3,794,809.21 3,336.80 3. Materials on Hand 416,905.48 0.00 4. Earned Subject to Retention 213,090,338.31 222,799.81 5. Mobilization 22,400,000.00 0.00 6. Total Work Completed 235,073,432.83 7. Deductions -32,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 235,458,338.31 222,799.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 222,799.81