Dept. of Trans. PROGRESS Serial No. Contract No. 23-202-19-42 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 73% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 057 Payment period ending: 07-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,797,410.19 402,156.96 2. a. Extra Work 17,467,776.41 357,574.75 b. Adustment Comp. 3,733,406.40 0.00 3. Materials on Hand 29,171.76 0.00 4. Earned Subject to Retention 215,027,764.76 759,731.71 5. Mobilization 22,400,000.00 0.00 6. Total Work Completed 237,398,593.00 7. Deductions -32,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 237,395,764.76 759,731.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 759,731.71