Dept. of Trans. PROGRESS Serial No. Contract No. 23-296-13-03 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 73% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 060 Payment period ending: 10-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 191,271,414.90 -2,767,045.43 2. a. Extra Work 23,497,334.58 5,185,157.16 b. Adustment Comp. 3,491,788.69 -303,298.32 3. Materials on Hand 4. Earned Subject to Retention 218,260,538.17 2,114,813.41 5. Mobilization 22,400,000.00 0.00 6. Total Work Completed 240,660,538.17 7. Deductions -32,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 240,628,538.17 2,114,813.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,114,813.41