Dept. of Trans. SEMI-FINAL Serial No. Contract No. 23-346-13-24 11-2T2184 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-5-R38.4/R47.3 6211-130 Progress payment No. 062 Payment period ending: 10-31-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 192,385,843.42 176,600.00 2. a. Extra Work 26,709,861.90 116,194.23 b. Adustment Comp. 5,085,563.14 -117,599.52 3. Materials on Hand 4. Earned Subject to Retention 224,181,268.46 175,194.71 5. Mobilization 22,400,000.00 0.00 6. Total Work Completed 246,581,268.46 7. Deductions -52,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 246,529,268.46 175,194.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 175,194.71