Dept. of Trans. PROGRESS Serial No. Contract No. 16-264-15-46 11-2T2304 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 11-SD-78-15.3/R16.3 PLUN-6211(117) Progress payment No. 038 Payment period ending: 09-20-16 PACIFIC RESTORATION GROUP INC PO BOX 429 PERRIS CA 92572 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 335,345.95 3,619.00 2. a. Extra Work 36,547.46 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 371,893.41 3,619.00 5. Mobilization 19,000.00 0.00 6. Total Work Completed 390,893.41 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 390,893.41 3,619.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,619.00