Dept. of Trans. PROGRESS Serial No. Contract No. 16-021-12-23 11-2T2504 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 82% Location: Federal Project: 11-SD-805-9.5/10.3 NONE Progress payment No. 015 Payment period ending: 01-20-16 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,623,179.90 234,444.44 2. a. Extra Work 134,178.86 17,286.50 b. Adustment Comp. 36,786.29 6,742.97 3. Materials on Hand 0.00 -12,565.16 4. Earned Subject to Retention 4,794,145.05 245,908.75 5. Mobilization 500,000.00 0.00 6. Total Work Completed 5,294,145.05 7. Deductions -250,200.00 -39,400.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,043,945.05 206,508.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 206,508.75