Dept. of Trans. PROGRESS Serial No. Contract No. 17-172-08-37 11-2T2514 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 100% Location: Federal Project: 11-SD-805-4.4/5.5 NONE Progress payment No. 002 Payment period ending: 06-20-17 CLEAN CUT LANDSCAPE INCORPORATED 7726 N FIRST ST UNIT 137 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,192.47 189,052.22 2. a. Extra Work 3,689.77 3,689.77 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 196,882.24 192,741.99 5. Mobilization 34,927.70 34,927.70 6. Total Work Completed 231,809.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 231,809.94 227,669.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 227,669.69