Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 17-278-13-32 11-2T2514 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 88% Location: Federal Project: 11-SD-805-4.4/5.5 NONE Progress payment No. 006 Payment period ending: 09-20-17 CLEAN CUT LANDSCAPE INCORPORATED 7726 N FIRST ST UNIT 137 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 499,710.17 45,396.00 2. a. Extra Work 60,516.71 1,130.73 b. Adustment Comp. -12,149.87 0.00 3. Materials on Hand 4. Earned Subject to Retention 548,077.01 46,526.73 5. Mobilization 36,766.00 0.00 6. Total Work Completed 584,843.01 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -4,652.67 -4,652.67 c. Reduction after 95% Comp. 9. Total pay to Contractor 580,190.34 41,874.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,874.06