Dept. of Trans. PROGRESS Serial No. Contract No. 17-297-13-35 11-2T2514 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 11-SD-805-4.4/5.5 NONE Progress payment No. 007 Payment period ending: 10-20-17 CLEAN CUT LANDSCAPE INCORPORATED 7726 N FIRST ST UNIT 137 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 642,132.57 142,422.40 2. a. Extra Work 62,926.96 2,410.25 b. Adustment Comp. -12,149.87 0.00 3. Materials on Hand 4. Earned Subject to Retention 692,909.66 144,832.65 5. Mobilization 36,766.00 0.00 6. Total Work Completed 729,675.66 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions 0.00 4,652.67 c. Reduction after 95% Comp. 9. Total pay to Contractor 728,675.66 148,485.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 148,485.32