Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-13-46 11-2T2604 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 19% Location: Federal Project: 11-SD-805-5.7/7.8 STPL-6211(121) Progress payment No. 004 Payment period ending: 11-20-18 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 969,825.45 379,863.81 2. a. Extra Work 36,908.31 19,144.50 b. Adustment Comp. 3. Materials on Hand 12,991.44 12,991.44 4. Earned Subject to Retention 1,019,725.20 411,999.75 5. Mobilization 610,345.45 0.00 6. Total Work Completed 1,617,079.21 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,630,070.65 412,999.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 412,999.75