Dept. of Trans. PROGRESS Serial No. Contract No. 19-322-13-37 11-2T2604 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 67% Location: Federal Project: 11-SD-805-5.7/7.8 STPL-6211(121) Progress payment No. 016 Payment period ending: 11-20-19 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92653 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,043,749.23 575,990.89 2. a. Extra Work 587,115.47 177,342.88 b. Adustment Comp. 114,901.92 0.00 3. Materials on Hand 856,975.55 -174,314.62 4. Earned Subject to Retention 7,602,742.17 579,019.15 5. Mobilization 1,220,690.90 0.00 6. Total Work Completed 7,966,457.52 7. Deductions -8,704.10 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,814,728.97 579,019.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 579,019.15