Dept. of Trans. PROGRESS Serial No. Contract No. 20-018-09-11 11-2T2604 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 79% Location: Federal Project: 11-SD-805-5.7/7.8 STPL-6211(121) Progress payment No. 018 Payment period ending: 01-20-20 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,961,550.99 421,907.42 2. a. Extra Work 900,620.11 19,077.43 b. Adustment Comp. 114,901.92 0.00 3. Materials on Hand 1,607,151.28 803,220.95 4. Earned Subject to Retention 9,584,224.30 1,244,205.80 5. Mobilization 1,220,690.90 0.00 6. Total Work Completed 9,197,763.92 7. Deductions -12,704.10 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,792,211.10 1,240,205.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,240,205.80