Dept. of Trans. PROGRESS Serial No. Contract No. 20-056-15-02 11-2T2604 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 84% Location: Federal Project: 11-SD-805-5.7/7.8 STPL-6211(121) Progress payment No. 019 Payment period ending: 02-20-20 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,911,033.26 949,482.30 2. a. Extra Work 977,881.60 77,261.49 b. Adustment Comp. 114,901.92 0.00 3. Materials on Hand 854,519.90 -752,631.38 4. Earned Subject to Retention 9,858,336.68 274,112.41 5. Mobilization 1,220,690.90 0.00 6. Total Work Completed 10,224,507.68 7. Deductions -12,704.10 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,066,323.48 274,112.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 274,112.41