Dept. of Trans. PROGRESS Serial No. Contract No. 20-141-18-14 11-2T2604 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 95% Location: Federal Project: 11-SD-805-5.7/7.8 STPL-6211(121) Progress payment No. 022 Payment period ending: 05-20-20 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,045,701.88 883,949.54 2. a. Extra Work 1,033,003.03 23,665.95 b. Adustment Comp. 275,363.87 0.00 3. Materials on Hand 28,591.81 -154,614.85 4. Earned Subject to Retention 11,382,660.59 753,000.64 5. Mobilization 1,220,690.90 0.00 6. Total Work Completed 12,574,759.68 7. Deductions -12,704.10 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,590,647.39 753,000.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 753,000.64