Dept. of Trans. PROGRESS Serial No. Contract No. 21-111-17-59 11-2T3304 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 11-SD-805-24.7/27.6 NONE Progress payment No. 037 Payment period ending: 04-20-21 ACCU CONSTRUCTION INC 2098 S GRAND AVE #A SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 752,602.25 3,000.00 2. a. Extra Work 40,903.89 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 793,506.14 3,000.00 5. Mobilization 10,000.00 0.00 6. Total Work Completed 803,506.14 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 803,506.14 3,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,000.00