Dept. of Trans. PROGRESS Serial No. Contract No. 25-142-16-05 11-2T3434 PROGRESS PAYMENT VOUCHER %complete: %time: 37% 30% Location: Federal Project: 11-SD-805-5.1/8.3 TPLN-6211(139) Progress payment No. 013 Payment period ending: 05-20-25 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,179,037.65 924,308.00 2. a. Extra Work 52,150.62 3,225.76 b. Adustment Comp. 18,200.00 0.00 3. Materials on Hand 262,238.19 -1.00 4. Earned Subject to Retention 9,511,626.46 927,532.76 5. Mobilization 3,102,275.29 0.00 6. Total Work Completed 12,351,663.56 7. Deductions -20,049.50 4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,593,852.25 931,532.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 931,532.76