Dept. of Trans. PROGRESS Serial No. Contract No. 22-111-17-09 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 28% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 007 Payment period ending: 04-20-22 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,309,256.57 1,557,763.17 2. a. Extra Work 175,951.86 114,866.83 b. Adustment Comp. 4,683.44 516.12 3. Materials on Hand 427,037.19 115,547.16 4. Earned Subject to Retention 11,916,929.06 1,788,693.28 5. Mobilization 5,877,175.00 1,237,300.00 6. Total Work Completed 17,367,066.87 7. Deductions -47.50 -10.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,794,056.56 3,025,983.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,025,983.28