Dept. of Trans. PROGRESS Serial No. Contract No. 22-259-15-44 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 56% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 012 Payment period ending: 09-20-22 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,427,065.78 2,816,492.18 2. a. Extra Work 405,504.70 3,421.53 b. Adustment Comp. 58,192.90 46,324.90 3. Materials on Hand 145,595.31 -31,340.69 4. Earned Subject to Retention 22,036,358.69 2,834,897.92 5. Mobilization 5,877,175.00 0.00 6. Total Work Completed 27,767,938.38 7. Deductions -47.50 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,913,486.19 2,844,897.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,844,897.92