Dept. of Trans. PROGRESS Serial No. Contract No. 22-294-17-39 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 50% 62% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 013 Payment period ending: 10-20-22 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,512,065.63 3,084,999.86 2. a. Extra Work 716,724.55 311,219.85 b. Adustment Comp. 58,192.90 0.00 3. Materials on Hand 124,895.01 -20,700.30 4. Earned Subject to Retention 25,411,878.09 3,375,519.41 5. Mobilization 5,877,175.00 0.00 6. Total Work Completed 31,164,158.08 7. Deductions -47.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 31,289,005.59 3,375,519.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,375,519.41