Dept. of Trans. PROGRESS Serial No. Contract No. 23-052-13-24 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 79% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 017 Payment period ending: 02-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,186,383.79 2,060,744.41 2. a. Extra Work 1,247,289.77 499,402.81 b. Adustment Comp. 82,143.35 0.00 3. Materials on Hand 391,430.02 0.00 4. Earned Subject to Retention 37,907,246.93 2,560,147.22 5. Mobilization 6,186,500.00 0.00 6. Total Work Completed 43,702,316.91 7. Deductions -50.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 44,093,696.93 2,560,147.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,560,147.22