Dept. of Trans. PROGRESS Serial No. Contract No. 23-111-19-31 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 88% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 019 Payment period ending: 04-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,699,778.19 2,212,523.45 2. a. Extra Work 1,343,538.25 21,959.15 b. Adustment Comp. -309,421.74 -393,132.80 3. Materials on Hand 603,331.97 62,268.74 4. Earned Subject to Retention 43,337,226.67 1,903,618.54 5. Mobilization 6,186,500.00 0.00 6. Total Work Completed 48,920,394.70 7. Deductions -5,050.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 49,518,676.67 1,903,618.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,903,618.54