Dept. of Trans. PROGRESS Serial No. Contract No. 23-230-22-32 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 100% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 023 Payment period ending: 08-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 48,208,821.40 1,492,436.79 2. a. Extra Work 1,462,650.08 12,932.44 b. Adustment Comp. -308,045.51 569.55 3. Materials on Hand 687,912.27 -33,423.13 4. Earned Subject to Retention 50,051,338.24 1,472,515.65 5. Mobilization 6,186,500.00 0.00 6. Total Work Completed 55,549,925.97 7. Deductions -33,850.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 56,203,988.24 1,462,515.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,462,515.65