Dept. of Trans. PROGRESS Serial No. Contract No. 23-261-14-54 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 100% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 024 Payment period ending: 09-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 50,128,011.08 1,919,189.70 2. a. Extra Work 1,477,386.06 14,735.98 b. Adustment Comp. -306,235.07 1,810.44 3. Materials on Hand 1,241,179.03 553,266.76 4. Earned Subject to Retention 52,540,341.10 2,489,002.88 5. Mobilization 6,186,500.00 0.00 6. Total Work Completed 57,485,662.07 7. Deductions -33,850.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 58,692,991.10 2,489,002.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,489,002.88