Dept. of Trans. PROGRESS Serial No. Contract No. 23-293-22-14 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 100% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 025 Payment period ending: 10-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 51,510,937.77 1,382,926.69 2. a. Extra Work 1,480,950.26 3,564.20 b. Adustment Comp. -269,599.89 36,635.18 3. Materials on Hand 1,021,527.40 -219,651.63 4. Earned Subject to Retention 53,743,815.54 1,203,474.44 5. Mobilization 6,186,500.00 0.00 6. Total Work Completed 58,908,788.14 7. Deductions -36,450.00 -2,600.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 59,893,865.54 1,200,874.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,200,874.44