Dept. of Trans. PROGRESS Serial No. Contract No. 23-355-12-21 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 027 Payment period ending: 12-20-23 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,381,461.25 579,534.93 2. a. Extra Work 1,504,268.63 5,764.96 b. Adustment Comp. -251,939.68 13,951.56 3. Materials on Hand 496,465.96 -242,168.60 4. Earned Subject to Retention 55,130,256.16 357,082.85 5. Mobilization 6,186,500.00 0.00 6. Total Work Completed 60,820,290.20 7. Deductions -41,450.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 61,275,306.16 357,082.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 357,082.85