Dept. of Trans. PROGRESS Serial No. Contract No. 24-085-14-04 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 030 Payment period ending: 03-20-24 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,380,523.54 -560,328.34 2. a. Extra Work 2,280,054.52 742,971.26 b. Adustment Comp. 104,227.29 0.00 3. Materials on Hand 63,417.00 -0.09 4. Earned Subject to Retention 55,828,222.35 182,642.83 5. Mobilization 6,186,500.00 0.00 6. Total Work Completed 61,951,305.35 7. Deductions -57,200.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 61,957,522.35 182,642.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 182,642.83