Dept. of Trans. PROGRESS Serial No. Contract No. 25-142-16-01 11-2T35U4 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 11-SD-5-37.4/52.6 NONE Progress payment No. 044 Payment period ending: 05-20-25 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,948,056.99 0.00 2. a. Extra Work 2,680,189.55 62,700.00 b. Adustment Comp. 95,790.43 -38,382.16 3. Materials on Hand 4. Earned Subject to Retention 56,724,036.97 24,317.84 5. Mobilization 6,186,500.00 0.00 6. Total Work Completed 62,910,536.97 7. Deductions -52,200.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 62,858,336.97 24,317.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,317.84