Dept. of Trans. PROGRESS Serial No. Contract No. 25-141-11-07 11-2T3644 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 48% Location: Federal Project: 11-SD-56-0.3/3.0 NONE Progress payment No. 016 Payment period ending: 05-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,926,893.83 409,279.84 2. a. Extra Work 4,289,802.79 664,500.27 b. Adustment Comp. 425,795.57 -4,000.00 3. Materials on Hand 67,096.17 -7,333.35 4. Earned Subject to Retention 12,709,588.36 1,062,446.76 5. Mobilization 924,520.00 0.00 6. Total Work Completed 13,567,012.19 7. Deductions -12,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,622,108.36 1,062,446.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,062,446.76