Dept. of Trans. PROGRESS Serial No. Contract No. 25-294-13-40 11-2T3644 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 55% Location: Federal Project: 11-SD-56-0.3/3.0 NONE Progress payment No. 021 Payment period ending: 10-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,668,621.24 20,569.00 2. a. Extra Work 4,809,946.00 163,395.18 b. Adustment Comp. 423,486.27 -2,309.30 3. Materials on Hand 4. Earned Subject to Retention 15,902,053.51 181,654.88 5. Mobilization 924,520.00 0.00 6. Total Work Completed 16,826,573.51 7. Deductions -17,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,809,573.51 181,654.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 181,654.88