Dept. of Trans. PROGRESS Serial No. Contract No. 25-262-14-55 11-2T36U4 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 66% Location: Federal Project: 11-SD-5-R37.4/R52.6 ACIM-051(996) 6211-156 Progress payment No. 023 Payment period ending: 09-20-25 FLATIRON-SKANSKA-STACY AND WITBECK A JOINT VENTURE 12121 SCRIPPS SUMMIT DR #400 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 64,353,904.25 2,488,433.37 2. a. Extra Work 7,317,813.27 1,009,745.62 b. Adustment Comp. 1,012,789.08 323,549.53 3. Materials on Hand 153,740.77 -317,684.91 4. Earned Subject to Retention 72,838,247.37 3,504,043.61 5. Mobilization 7,252,000.00 0.00 6. Total Work Completed 79,936,506.60 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 80,085,247.37 3,499,043.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,499,043.61