Dept. of Trans. PROGRESS Serial No. Contract No. 06-205-14-06 11-352304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 11-SD-5-R13.0/R15.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 07-20-06 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 394,668.50 119,593.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 394,668.50 119,593.00 5. Mobilization 6. Total Work Completed 394,668.50 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -19,733.43 -5,979.65 b. Unsatisfactory Prog. 0.00 7,417.40 c. Reduction after 95% Comp. 9. Total pay to Contractor 364,935.07 121,030.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 121,030.75