Dept. of Trans. FINAL Serial No. Contract No. 12-041-07-53 11-402704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-IMP-8-R7.4/R7.9 Federal Project: ACHS-082(102) IMG-082(102) Progress payment No. 06 Payment period ending: 11-08-11 HAZARD CONSTRUCTION P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 322,299.10 0.00 2.a. Extra Work 16,529.94 3,666.00 b. Adjustment Comp. -455.03 0.00 3. Materials on Hand 4. Earned Subject to Retention 338,374.01 3,666.00 5. Mobilization 6. Total Work Completed 338,374.01 7. Deductions 0.00 22,958.50 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 338,374.01 26,624.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,624.50