Dept. of Trans. PROGRESS Serial No. Contract No. 13-294-14-23 11-404304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 4% 11-SD-5-R23.9/R25.5 Federal Project: ACHS-051(624) NHPI-G005-1(624 Progress payment No. 02 Payment period ending: 10-20-13 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 128,508.60 124,486.60 2.a. Extra Work 292.97 292.97 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 128,801.57 124,779.57 5. Mobilization 140,000.00 140,000.00 6. Total Work Completed 268,801.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 268,801.57 264,779.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 264,779.57