Dept. of Trans. PROGRESS Serial No. Contract No. 13-353-15-34 11-404304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 15% 11-SD-5-R23.9/R25.5 Federal Project: ACHS-051(624) NHPI-G005-1(624 Progress payment No. 04 Payment period ending: 12-20-13 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 669,593.80 238,188.00 2.a. Extra Work 19,381.86 18,476.89 b. Adjustment Comp. 3. Materials on Hand 3,861.00 3,861.00 4. Earned Subject to Retention 692,836.66 260,525.89 5. Mobilization 266,000.00 56,000.00 6. Total Work Completed 954,975.66 7. Deductions -8,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 950,836.66 312,525.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 312,525.89