Dept. of Trans. PROGRESS Serial No. Contract No. 14-083-14-41 11-404304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 27% 11-SD-5-R23.9/R25.5 Federal Project: ACHS-051(624) NHPI-G005-1(624 Progress payment No. 07 Payment period ending: 03-20-14 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,015,227.83 265,777.28 2.a. Extra Work 46,732.62 14,501.65 b. Adjustment Comp. -2,740.02 -2,740.02 3. Materials on Hand 11,895.66 0.00 4. Earned Subject to Retention 2,071,116.09 277,538.91 5. Mobilization 280,000.00 0.00 6. Total Work Completed 2,339,220.43 7. Deductions -6,200.00 4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,344,916.09 281,538.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 281,538.91