Dept. of Trans. PROGRESS Serial No. Contract No. 16-050-13-51 11-405504 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 27% Location: Federal Project: 11-SD-8-6.9/8.2 HSNH-008-1(316) Progress payment No. 006 Payment period ending: 02-20-16 HAZARD CONSTRUCTION COMPANY PO BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 419,338.50 136,841.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 419,338.50 136,841.50 5. Mobilization 250,000.00 0.00 6. Total Work Completed 669,338.50 7. Deductions -6,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 663,338.50 131,841.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 131,841.50