Dept. of Trans. PROGRESS Serial No. Contract No. 17-265-13-57 11-405704 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 11% Location: Federal Project: 11-SD-76-32.6/33.3 SSTG-S076(30) Progress payment No. 003 Payment period ending: 09-20-17 LB CIVIL CONSTRUCTION INC 324 EAST VALLEY PKWY ESCONDIDO CA 92025 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 837,564.30 489,954.55 2. a. Extra Work 7,042.75 7,042.75 b. Adustment Comp. 6,411.65 5,586.65 3. Materials on Hand 51,229.14 4,019.70 4. Earned Subject to Retention 902,247.84 506,603.65 5. Mobilization 285,750.00 95,250.00 6. Total Work Completed 1,136,768.70 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,185,997.84 599,853.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 599,853.65