Dept. of Trans. PROGRESS Serial No. Contract No. 19-055-08-38 11-405704 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 58% Location: Federal Project: 11-SD-76-32.6/33.3 SSTG-S076(30) Progress payment No. 020 Payment period ending: 02-20-19 LB CIVIL CONSTRUCTION INC 324 EAST VALLEY PKWY ESCONDIDO CA 92025 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,511,274.35 43,971.87 2. a. Extra Work 485,476.08 3,966.90 b. Adustment Comp. 21,109.81 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,017,860.24 47,938.77 5. Mobilization 381,000.00 0.00 6. Total Work Completed 5,398,860.24 7. Deductions -16,016.50 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,382,843.74 45,938.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,938.77