Dept. of Trans. PROGRESS Serial No. Contract No. 19-082-07-09 11-405704 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 62% Location: Federal Project: 11-SD-76-32.6/33.3 SSTG-S076(30) Progress payment No. 021 Payment period ending: 03-20-19 LB CIVIL CONSTRUCTION INC 324 EAST VALLEY PKWY ESCONDIDO CA 92025 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,525,316.35 14,042.00 2. a. Extra Work 484,891.94 -584.14 b. Adustment Comp. 21,109.81 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,031,318.10 13,457.86 5. Mobilization 381,000.00 0.00 6. Total Work Completed 5,412,318.10 7. Deductions -16,016.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,396,301.60 13,457.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,457.86