Dept. of Trans. PROGRESS Serial No. Contract No. 12-298-09-02 11-406004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 29% 11-SD-5-26.8/52.9 Federal Project: ACST-X073(95) P Progress payment No. 02 Payment period ending: 10-20-12 S & B ENGINEERING P O BOX 1400 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 191,520.54 182,797.64 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 191,520.54 182,797.64 5. Mobilization 47,500.00 47,500.00 6. Total Work Completed 239,020.54 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 239,020.54 230,297.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 230,297.64