Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 12-339-11-19 11-406004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 51% 11-SD-5-26.8/52.9 Federal Project: ACST-X073(95) P Progress payment No. 04 Payment period ending: 11-20-12 S & B ENGINEERING P O BOX 1400 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 326,476.69 0.00 2.a. Extra Work 27,290.00 27,290.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 353,766.69 27,290.00 5. Mobilization 50,000.00 0.00 6. Total Work Completed 403,766.69 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 393,766.69 27,290.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,290.00