Dept. of Trans. PROGRESS Serial No. Contract No. 16-298-17-04 11-406404 PROGRESS PAYMENT VOUCHER %complete: %time: 27% 20% Location: Federal Project: 11-SD-54-1.8/1.9 HSNH-PGX 0731-16E Progress payment No. 004 Payment period ending: 10-20-16 L B CIVIL CONSTRUCTION INC 11585 SORRENTO VALLEY RD #104 SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 769,908.80 278,775.10 2. a. Extra Work 12,601.37 0.00 b. Adustment Comp. 2,217.00 2,217.00 3. Materials on Hand 182,851.13 51,110.18 4. Earned Subject to Retention 967,578.30 332,102.28 5. Mobilization 320,150.00 67,400.00 6. Total Work Completed 1,104,877.17 7. Deductions -3,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,284,728.30 398,502.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 398,502.28