Dept. of Trans. PROGRESS Serial No. Contract No. 17-025-11-14 11-406404 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 35% Location: Federal Project: 11-SD-54-1.8/1.9 HSNH-PGX 0731-16E Progress payment No. 007 Payment period ending: 01-20-17 LB CIVIL CONSTRUCTION INC 324 EAST VALLEY PKWY ESCONDIDO CA 92025 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,310,302.48 222,031.63 2. a. Extra Work 106,426.92 46,344.74 b. Adustment Comp. 2,217.00 0.00 3. Materials on Hand 182,906.72 -51,975.12 4. Earned Subject to Retention 1,601,853.12 216,401.25 5. Mobilization 320,150.00 0.00 6. Total Work Completed 1,739,096.40 7. Deductions -9,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,913,003.12 216,401.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 216,401.25