Dept. of Trans. PROGRESS Serial No. Contract No. 14-295-08-42 11-406504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 82% 11-SD-15-R36.8/R40.8 Federal Project: HSNH-015-1(231) Progress payment No. 04 Payment period ending: 10-20-14 WESTERN RIM CONSTRUCTORS INC 912 S ANDREASEN DR SUITE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,322,441.24 749,962.86 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 62,012.38 -371,640.62 4. Earned Subject to Retention 2,384,453.62 378,322.24 5. Mobilization 291,644.00 0.00 6. Total Work Completed 2,614,085.24 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,671,097.62 378,322.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 378,322.24