Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-140-13-21 11-406504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-15-R36.8/R40.8 HSNH-015-1(231) Progress payment No. 009 Payment period ending: 12-31-14 WESTERN RIM CONSTRUCTORS INC 912 S ANDREASEN DR SUITE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,738,320.35 0.00 2. a. Extra Work 13,177.69 1,370.29 b. Adustment Comp. 250,285.33 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,001,783.37 1,370.29 5. Mobilization 291,644.00 0.00 6. Total Work Completed 3,293,427.37 7. Deductions -10,000.00 8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,283,427.37 9,370.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,370.29