Dept. of Trans. PROGRESS Serial No. Contract No. 14-356-07-57 11-406604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 4% 6% 11-SD-76-R4.2/R7.6 Federal Project: HSNH-P076(29) Progress payment No. 02 Payment period ending: 12-20-14 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY PLACE SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 260,141.04 189,741.04 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 260,141.04 189,741.04 5. Mobilization 6. Total Work Completed 260,141.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 260,141.04 189,741.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 189,741.04