Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-08-35 11-406704 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 24% Location: Federal Project: 11-SD-5-R58.1/R72.4 NHPI-051(627) Progress payment No. 007 Payment period ending: 03-20-15 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,297,546.07 2,457,932.40 2. a. Extra Work 135,473.30 7,854.00 b. Adustment Comp. 15,259.13 876.00 3. Materials on Hand 164,883.95 19,558.50 4. Earned Subject to Retention 12,613,162.45 2,486,220.90 5. Mobilization 1,829,700.00 0.00 6. Total Work Completed 14,277,978.50 7. Deductions -11,000.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 14,431,862.45 2,488,220.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,488,220.90