Dept. of Trans. PROGRESS Serial No. Contract No. 15-146-08-51 11-406904 PROGRESS PAYMENT VOUCHER %complete: %time: 0% 6% Location: Federal Project: 11-SD-8-R25.9/R32.2 STPI-008-1(314) Progress payment No. 002 Payment period ending: 05-20-15 DALEY CORPORATION 12570 HIGHWAY 67 LAKESIDE CA 92040 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,027.90 39,890.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 42,027.90 39,890.40 5. Mobilization 6. Total Work Completed 42,027.90 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 42,027.90 39,890.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,890.40